fbpx

Four lane upgrade road construction



Client : Ministère des Transports du Québec Year : 2006-2010 Localisation : Road 175 – Saguenay - Québec

Description :

KM 84 to 96 and KM 215 to 219

  • Clearing of vegetation
  • Grubbing and stripping
  • Overburden excavation
  • Drilling/blasting
  • Rock loading/transportation
  • Culverts installation
  • Formwork and concreting for bridges
  • Crushing
  • Paving
  • Hydroseeding

Others achievements

ROMAINE-4 – TAILRACE AND BYPASS CAP

Excavating the tailrace cap, concreting the permanent bypass cap and building a conduit bedplate Inject...

Read More
138 ROAD – 138 ROAD EXTENSION LOT1 AND 1A

Construct a remote section of 138 Road, about 14 km long Drilling and blasting foundations...

Read More
PORT-DANIEL-GASCON – RELOCATION OF THE RAILROAD LINE

Excavation of the 1st class and reconstruction of an approximately two-kilometre section of the existing...